Co/Tri-generation programme in Hospitals (Phase 2)

Estimated Project Cost: ZAR 2.3 billion
Status: Financial Close process
Expected Delivery Model: Regulated PPP
Sector: Energy
Project Status: In the Market

Project Background and Scope

The Design, construction, financing, maintenance and operations of tri-generation (electricity, heating and cooling) plants (app. 2MW each) at the following 6 hospitals, viz.:

  • Chris Hani Baragwanath (Financial close)
  • Charlotte Maxeke
  • Dr. George Mukhari
  • Steve Biko
  • New Natalspruit
  • Bheki Mlangeni Hospital

Progress is as follows

  • The preferred bidder was selected for the implementation of a Co-generation Plant at Chris-Hani Baragwanath Hospital, for a 2.5 MW base load of power circa R100 million.
  • The contractual negotiations with the preferred bidder on going and expected to conclude in August 2017.

The remainder of the five hospitals will be
issued to the prequalified bidders post-financial close of CHB Hospital.